- Reconnect ECM/PCM connector E (31P).
- Turn the ignition switch ON (II).
- Measure voltage between body ground and ECM/PCM connector terminals A2 and A3 individually.
ECM/PCM CONNECTOR A (31P)
Wire side of female terminals
Is there battery voltage?
YES |
- Go to step 47. |
NO |
- Go to step 41. |
- Turn the ignition switch OFF.
- Remove the PGM-FI main relay 1 (A).
- Turn the ignition switch ON (II).
| |
- Measure voltage between the PGM-FI main relay 1 4P connector terminal No. 2 and body ground.
Wire side of female terminals
Is there battery voltage?
YES |
- Go to step 45. |
NO |
- Repair open in the wire between the No. 6 ECU (ECM/PCM) (15A) fuse and the PGM-FI main relay 1. |
- Turn the ignition switch OFF.
- Check for continuity between the PGM-FI main relay 1 4P connector terminal No. 1 and ECM/PCM connector terminals A2 and A3 individually.
Wire side of female terminals
Is there continuity?
YES |
- Replace the PGM-FI main relay 1. |
NO |
- Repair open in the wire between the PGM-FI main relay 1 and the ECM/PCM (A2, A3). |
|